From airfield to district: the whole story, dated and sourced.

Eighty-one years of aviation, fifty years of argument over the land, one masterplan, a tender gold rush, and a construction site the size of a neighborhood. This is the complete record — every event links to the article or document it came from.

Aircraft landing at Sde Dov
Aircraft landing at Sde DovChen Haik / PikiWiki
Historical Tel Aviv presentation
Historical Tel Aviv presentationsdedov.co.il
Sde Dov airport entrance sign
Sde Dov airport entrance signsdedov.co.il
AirportPlanningTendersConstructionMarketInfrastructureEnvironment

1938

  1. 3 Sept 1938AIRPORT
    Sde Dov (Dov Hoz) Airport opens

    The airfield opened on 3 September 1938 during the Arab Revolt, as Tel Aviv's alternative to Lydda. Palestine Airways flew from here; it later became an RAF base and the home of Israel's first air-force squadron. Wikipedia

2012

  1. 3 Jul 2012PLANNING
    Masterplan TA/3700 approved for the northwest Tel Aviv coast

    The outline plan for about 1,900 dunams of the northwest coast is approved, the envelope that later holds district plan TA/4444. sdedov.co.il

  2. 5 Dec 2012PLANNING
    Government approves evacuation of Sde Dov airport

    The government backs trading the airfield for housing, the decision that starts the long close-down. sdedov.co.il

2014

  1. 3 Sept 2014PLANNING
    Program set at 16,000 housing units

    The steering committee, with city engineer Oded Gvuli, updates the program to 16,000 homes — the figure that still defines the district. sdedov.co.il

2015

  1. 6 Jun 2015PLANNING
    Defense Ministry takes ₪1B for early evacuation

    The state pays about a billion shekels so the army will leave the field before the original timetable. sdedov.co.il

2016

  1. 26 Feb 2016PLANNING
    Supreme Court sets evacuation for January 2019

    The court postpones the final evacuation date to January 2019, locking the close of the 81-year airfield. sdedov.co.il

2019

  1. 30 Jun 2019AIRPORT
    Sde Dov Airport closes after 81 years

    The last flight leaves; the final IAF sortie goes to Hatzor, and Eilat receives ₪400M in compensation. The field had moved 703,649 passengers in its last full year. ITN

  2. 31 Jul 2019AIRPORT
    Runway demolition begins

    Demolition of the runway starts; the site is fully vacated by early 2020. Only the control tower is kept as a historic building. Wikipedia

2020

  1. 10 Feb 2020AIRPORT
    Evacuation of Sde Dov is complete

    After 81 years, the IDF and civil evacuation of the airfield is finished. sdedov.co.il

  2. 12 Mar 2020PLANNING
    District plan TA/4444 validated

    The Sde Dov district plan is validated: about 16,000 homes on 1,500 dunams, three complexes, parks, hotels, and two kilometres of beach. sdedov.co.il

2021

  1. 1 Mar 2021TENDERS
    ILA issues the first Sde Dov housing tender

    The Israel Land Authority tenders 1,916 units in the Eshkol section, including 324 long-term rental apartments. Globes

  2. 23 Aug 2021TENDERS
    Record first-tender results: ₪4.4B for 1,540 homes

    Winners pay about ₪2.8M in land per apartment, 6.5 times the minimum. Avisror, K.M. Madaf 5, Meshulam Levinstein + Allied, G.Z. Madaf 35, and Israel Canada (480 units, ~₪1.3B) take plots. Globes

  3. 2 Dec 2021TENDERS
    Shikun & Binui wins 324 long-term rental units

    Lot 109 in Eshkol goes to Shikun & Binui through the government Dira LeHaskir tender. sdedov.co.il

2022

  1. 22 Mar 2022TENDERS
    Follow-up tender cools: 241 units for ₪654M

    A smaller Eshkol follow-up closes at about ₪2.71M of land per unit, well below the 2021 frenzy. Globes

  2. 28 Mar 2022TENDERS
    Claude Nahmias wins a RAMI tender in Eshkol

    Nahmias Group wins an Israel Land Authority tender to build apartments in Complex A / Eshkol, the plot that becomes UTOPIA on lot 103. sdedov.co.il

  3. 12 Apr 2022TENDERS
    Shikun & Binui wins 511 more rental units

    A second Dira LeHaskir win gives Shikun & Binui lot 106 — 511 long-term rental apartments. sdedov.co.il

2023

  1. 10 May 2023PLANNING
    First Eshkol design plans approved

    About two years after the first big tender, the local committee approves the first architectural design plans in the southern complex. sdedov.co.il

2024

  1. 20 Feb 2024PLANNING
    Reut Rehabilitation Hospital campus approved

    A new campus for Reut Hospital, relocating from Yad Eliyahu, is approved on the former airfield. sdedov.co.il

  2. 26 Mar 2024CONSTRUCTION
    First building permit in the district — Rainbow excavation

    Israel Canada's RAINBOW on lot 111 receives the first excavation-and-shoring permit in Sde Dov. sdedov.co.il

  3. 25 Jul 2024MARKET
    Dimri buys Mor Group's lot 107 for ₪1.1B

    Y.H. Dimri enters Sde Dov after Hanan Mor's ₪3.2B debt settlement, paying ₪1.1B for land Mor had won at ₪1.5B in 2021. sdedov.co.il

  4. 19 Aug 2024PLANNING
    Local committee gives final validation to Central and North plans

    The detailed plans for the two remaining complexes — thousands of homes north of Eshkol — are finally validated. sdedov.co.il

  5. 1 Sept 2024TENDERS
    ILA launches its biggest wave: 7,159 units

    Ten tenders in the Center and North plans go to market, land for more than 7,100 homes, with a headline value of about ₪25B. Globes

  6. 11 Nov 2024CONSTRUCTION
    First cornerstone laid at ASHIRA

    Avisror lays the first cornerstone in the district on lot 101, the moment construction of the new neighborhood becomes visible. sdedov.co.il

  7. 25 Dec 2024TENDERS
    All Sde Dov tenders postponed after two appeals

    Wind-regime and land-rights appeals against the detailed plans freeze the mega-tender; further postponements follow into 2025. Globes

2025

  1. 19 Feb 2025TENDERS
    Central-district winners: 4,191 units for about ₪6B

    Land prices come in about 40% below 2021. Winners include Israel Brothers, Gindi Holdings (two plots), Electra Residence + Dan Nadlan (Nahor), Luzon Ronson, Hagag Group (350 units, ~₪756M), and A.A.I. Abu + Tomer Koko. Ynet

  2. 4 Mar 2025TENDERS
    Prashkovsky wins both long-term-rental tenders (966 units)

    Bidding with Dira LeHaskir, Prashkovsky takes both rental tenders — 966 apartments that will not be sold on the private market. Jerusalem Post

  3. 16 Mar 2025TENDERS
    Dan Real Estate buys a private-land plot for ~₪600M

    260 units plus 300 sqm of commerce, in a combination deal that beat Gindi, Electra, Azorim, and Zemach Hammerman. Calcalist

  4. 26 Mar 2025TENDERS
    North-district tenders close: 2,744 units, ₪4.59B

    Winners include Y.H. Dimri (275), Calanit, Shikun & Binui + Shapir, Aviv/Melisron (320), Euro Israel (360), Luzon Ronson + Shimon Amir, Yossi Avrahami, Tashluz (177), Mediterranean Towers (300 senior units), and A.M. Israel + Union Living (rental). A first-four-tenders subset of 1,737 units is reported the next day. Ynet

  5. 3 Jun 2025MARKET
    Gindi prices VOGUE from ₪49,000 per sqm

    The Central-complex launch undercuts the district average by tens of percent; around 700 apartments sell within weeks. Nadlan Center

  6. 11 Jul 2025MARKET
    Hagag launches FIRST

    The ODA-designed 45-floor sea-line tower on lot 2270 goes to market; 46 sales follow in two months. Calcalist

  7. 27 Aug 2025MARKET
    Israel Canada's average Rainbow deal hits ₪11M

    A record average for the project: 234 units sold for ₪2B. Calcalist

  8. 17 Sept 2025PLANNING
    Court approves the Big Bloc rights table for 1,892 owners

    A historic ruling settles the division of the privately owned land inside the old airport — the 50-year fight over HaGush HaGadol. sdedov.co.il

  9. 1 Oct 2025CONSTRUCTION
    Rainbow receives a full building permit

    Israel Canada's RAINBOW on lot 111, which already held the district's first excavation permit, receives a full building permit. sdedov.co.il

  10. 22 Dec 2025MARKET
    Dimri launches Dimri Yama TLV from ₪3.75M

    458 units on lot 107, about ₪1.07B of investment, two-room apartments from ₪3.75M. sdedov.co.il

2026

  1. 1 Jan 2026CONSTRUCTION
    Rainbow moves to execution with Ashtrom

    Israel Canada picks Ashtrom as contractor for ~₪736M. Works start in January 2026 on the tower, reported 70% pre-sold. Mako

  2. 21 Jan 2026PLANNING
    Six Center and North plots approach building permits

    Design-plan approvals are fast-tracked a year after the land was marketed. Globes

  3. 27 Jan 2026MARKET
    ZOHI launches

    Levinstein, Mivne, and Metropolis/Allied put 230 low-rise units on lot 110 on sale from ₪70,000 per sqm. Globes

  4. 4 Feb 2026ENVIRONMENT
    PFAS groundwater contamination announced

    The Environment Ministry and the Israel Land Authority disclose firefighting-foam chemicals in the old airport's groundwater. Investigations widen; delays to the ~16,000-unit build-out are possible. Globes

  5. 12 Mar 2026CONSTRUCTION
    ASHIRA receives a full building permit

    Avisror's lot 101, which tested clean of contamination, gets a full permit — the first among the flagship marketed towers. sdedov.co.il

  6. 14 May 2026TENDERS
    Remaining tenders stall after 12 postponements

    A 217-unit Central-district tender has been postponed 12 times since September 2024; other leftover tenders are also stuck. Globes

  7. 2 Jun 2026MARKET
    Sales slowdown across the district

    Q1 filings show the pace collapsing. Israel Canada has sold about 300 units at ₪85,700/sqm on average; a late-May report says almost half of Dimri's sales were to the controlling shareholder. Globes

  8. 8 Jul 2026INFRASTRUCTURE
    Green Line light-rail progress update

    The municipality presents a southern-section timetable, with Mayor Huldai. Four stations will serve the district: Propes, Nofei Yam, Einstein, and Zahara Levitov. sdedov.co.il

  9. 5 Aug 2026ENVIRONMENT
    First buyer lawsuit over contamination

    An option-holder sues Gindi Holdings for a ~₪500K refund after the PFAS findings. CTech

  10. 16 Aug 2026INFRASTRUCTURE
    Fifth water line gets a green light

    Approval of Tel Aviv's fifth water line is framed as paving the way to occupying Sde Dov. sdedov.co.il